ZUMV2 Release scope
...
European slots (5) | American slots (25 & 26) | |||
---|---|---|---|---|
PRE-PROD | PROD | PRE-PROD | PROD | |
ZUMV2 Sprint 1 | 16.04.2024 ![]() | 23.04.2024 | 16.04.2024 ![]() | 23.04.2024 |
ZUMV2 Sprint 2 | 27.08.2024 (at earliest) | 03.09.2024 (at earliest) | 07.05.2024 | 14.05.2024 |
ZUMV2 Sprint 3 | 27.08.2024 (at earliest) | 03.09.2024 (at earliest) | 28.05.205 | 04.06.2024 |
ZUMV2 Sprint 4 | 27.08.2024 (at earliest) | 03.09.2024 (at earliest) | 18.06.2024 | 25.06.2024 |
ZUMV2 Sprint 5 | 27.08.2024 (at earliest) | 03.09.2024 (at earliest) | 09.07.2024 | 16.07.2024 |
ZUMV2 Sprint Stab | 27.08.2024 (at earliest) | 03.09.2024 (at earliest) | 30.07.2024 | 06.08.2024 |
Please note that the European slot installation dates after the end of the freeze will be reviewed and is subject to modificationare subject to modification and will be updated accordingly once the unfreeze date is known.
What has been released ?
Ui tabs | |||||
---|---|---|---|---|---|
|
...